Demolition of 126 Houses for Fleetwood Housing

Location: Fleetwood

Client: Regenda

Duration: 33 week

Completion: 01/04/2019

Project Scope:

Asbestos Removal & Mechanical Demolition of 126 houses, Top soiling & seeding of 36,000m2 and knee rail fence install to demolition footprint

Bradley Group were hired to complete the Asbestos Removal and Mechanical Demolition of 126 houses in Fleetwood.

Additional Works

After the demolition works were completed, Bradley Group were also responsible for the top soiling and seeding of 36,000m2 of ground, plus knee rail fencing was also installed to the demolition footprint.