The scope of works included an extensive soft strip demolition and removal of all materials within the original Terminal 2 structure, reducing the areas back to shell and core. The works required management of sufficient resources to supplement the different phases of the project interfacing with multiple trades to ensure critical target programmes were achieved.
Working Within The Live Airport
Due to the nature of the works taking place within a Live Airport Environment, additional control measures were in place to mitigate any risk to disruption of Airport activities. The use of extensive modern electrical plant minimised the environmental impact of the works and contributed to our Net zero carbon neutral project goals.
Internal Soft Strip
Exterior Airport Structure Demolition
In addition to the large scale soft strip, Bradley Group were also tasked with the deconstruction and demolition of airside node & link bridge structures, internal lift shafts, structural alterations, screed & slab removal.